Showing posts with label Delay in possession. Show all posts
Showing posts with label Delay in possession. Show all posts
Consumer Forum directed a builder to pay Rs. 11.50 Lakhs for failure to provide OC.
.jpg)
Before investing your hard earned money in a house, make sure you have chosen a reputed builder
After
staying in a leave and license accommodation
for many
years,
an enthusiast dreaming to
have his own house, eventually bought a flat in Borivli
by taking a home loan. Since
shifting was a priority to save the dual cost
of the lease rental and the loan
repayment on his new purchase,
he readily signed a letter stating
that he was being given
the keys
to his flat by the builder pending the completion
of the building “for carrying out furniture work”
Thane based Builder ordered to pay Rs. 7.5 Lakhs for giving a Smaller Flat examines Adv. R. P. Rathod.
The Maharashtra State Consumer Disputes Redressal Commission recently ordered a Thane based Builder M/S Animesh Enterprises to pay Mr. Mangesh. Ghadge. a total of Rs 7.5 Lakhs for causing a deficit of 150 sq ft area. Alternatively, the builder will have to provide 150sq ft area to the Complainant.
Adv. R. P. Rathod. throws light on the facts of the Case: On June 6, 1999, Ghadge and the builders entered into an agreement. The builder had agreed to sell the flat measuring 600 sq ft on the 3rd floor of the proposed building. The 222.4 sq meter land at Lohar Lane, Thane, on which the construction was set to take place, belonged to Ghadge. The agreement also provided that the completed flat would be handed over on or before November 27, 2001.
Builder to pay Compensation for Delay in handing over possession of Flat
An analysis of
the judgment passed by the National Consumer Disputes Redressal Commission, New
Delhi by Adv. R. P. Rathod.
The said judgment is issued in the
matter of Mrs. Veena Khanna of New Delhi Vs M/s. Ansal Properties and
Adharshila Towers, New Delhi: Before National Consumer Disputes Redressal
Commission, New Delhi: Order dated 9th July 2007.
Builder to pay Buyer Rs 1.5 Lakhs for delay of 9 months in handing over possession.
In
a recent Court Ruling - Developer gives buyer apartments 9 months late, with
incomplete documents, no Electricity or Water Connection
An Analysis of
the said Judgment the passed by the State Consumer
Disputes Redressal Forum by Adv. R. P. Rathod.